Construction sites on the campus

14.02.2024 -  

In 2024, it will still be necessary to close various areas and roads as part of EK2020.


1st section: Heizungstrasse between buildings 21 / 21.1 / 19 (expected Nov. 23 - Feb. 24)
1.1 Impairments
- Complete closure to car traffic in the area of the vehicle fleet (Building 21 / 21.1)
- Closure of the intersection of buildings 19 / 21 / 16 / 15 to integrate building 19
1.2 Securing
- Fire department access at building 20 - rear entrance
- Delivery to building 19 - south/east side

 

2nd section: Heating street building 15 (incl. 15.1/2) (expected Jan. 24 - Apr. 24)
2.1 Impairments
- Routing in street between buildings 16 and 15, complete closure for parking vehicles, partial closure for deliveries
- Partial closure of areas in the inner courtyard of building 15
2.2 Safeguarding
- Fire department access and entrances to buildings 15 and 16
- Keeping the intersection of buildings 14 / 15 / 12 / 16 clear
- Securing delivery to building 16 nitrogen tank

 

3rd section: Heating street building 14 (incl. 14.1-3) to building 04 Rectorate (expected Apr. 24 - Sep. 24)
3.1 Impairments
- Routing in street between buildings 14 and 13, complete closure for parking vehicles, partial closure for deliveries
- Impairments to the use of building 14.3
- Partial closure of areas in the inner courtyard of building 14
- Partial closure of intersection area of buildings 14 / 15 / 16 / 12
- Partial closure of intersection area in front of buildings 04 / 05 / 13
3.2 Securing
- Fire department access and entrances to buildings 16 West, 14 and 13
- At least one of the above-mentioned intersections must be kept clear to secure the fire department access routes
- Securing deliveries to building 14
- Securing deliveries to buildings 12 and 13

 

4th section: Heating and cooling line building 14 / 15 and west of building 16 (expected Feb. 24 - Dec. 24)
4.1 Impairments
- Routing in road between buildings 15 / 14, complete closure for car traffic
- Partial closure in the area of the intersection of buildings 14 / 15 / 16
- Partial closure (half-sided road closure) in the area west of building 16, complete closure of all parking spaces
4.2 Securing
- Fire department access north to the entrances to buildings 14-East and 15-West
- Fire department access to buildings 14 / 15 / 16

Due to incalculable circumstances, there may be temporal and local adjustments in the process.

Last Modification: 15.02.2024 - Contact Person: