Final Report

The final report must be submitted 60 days after the end of the project and, in addition to the information in a periodic report, contains the following:

  • Results, conclusions and socio-economic impacts of the project
  • Social impacts (gender equality actions, ethical issues, …) including a plan to exploit and disseminate the findings

A certificate on the financial statements / audit certificate must be submitted by a beneficiary if this partner has applied for a funding sum of at least €325,000.

The Commission has 90 days after receipt of the reports during which it may audit them and make the corresponding periodic or final payments.