Budget shifts
Budget shifts without changing the GA (without EU approval) are possible:
- if project tasks and their distribution between partners do not change,
- if budget is shifted from one partner to another partner, and
- when budget is shifted from one budget category to another budget category (same partner).
Budget shifts with change of GA (with EU approval) are possible:
- if there is a "significant change" in the work; and
- if the need for additional subcontracts arises during the project.